Client: Portfolio Landlord
Architect & Designer: CH+MRP Architects
Contract Administrator: CHMRP Architects
Duration: 50 weeks
Value: £600,000
Details:
- Cut & carve scheme to 3 residential units
- Demolition and soft strip through out
- Various structural steel installation works
- New 2 storey rear addition
- New Bauder felt roof overlay system
- New sash windows and doors throughout
- New gas, electric, and water supplies
- New mechanical and electrical installation throughout – CDP
- Full fit out to all 3 units including new kitchens, bathrooms, wardrobes
- Communal refurbishment including integrated fire alarm
- Decoration to lower ground floor unit
- Garden clearance, slab, and drainage works
Key Objectives / Challenges:
- Dealing with TFL regarding the utility installations
- Ongoing extensive variations
- Deliveries on a Red Route